New Updates

Points That Site Engineer Should Remember

Points That Site Engineer Should Remember
Following are few general points to remember for civil site engineers to make the construction work easier while maintaining quality of construction.
·         Lapping is not allowed for the bars having diameters more than 36 mm.
·         Chair spacing maximum spacing is 1.00 m (or) 1 No per 1m2.
·         For dowels rod minimum of 12 mm diameter should be used.
·         Chairs minimum of 12 mm diameter bars to be used.
·         Longitudinal reinforcement not less than 0.8% and more than 6% of gross C/S.
·         Minimum bars for square column is 4 No’s and 6 No’s for circular column.
·         Main bars in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and the distributors not less than 8 mm and not more than 1/8 of slab thickness.
·         Minimum thickness of slab is 125 mm.
·         Dimension tolerance for cubes + 2 mm.
·         Free fall of concrete is allowed maximum to 1.50m.
·         Lap slices not be used for bar larger than 36 mm.
·         Water absorption of bricks should not be more than 15 %.
·         PH value of the water should not be less than 6.
·         Compressive strength of Bricks is 3.5 N / mm2.
·         In steel reinforcement binding wire required is 8 kg per MT.
·         In soil filling as per IS code, 3 samples should be taken for core cutting test for every 100m2.

Density of Materials:
Material
Density
Bricks
1600 – 1920 kg/m3
Concrete block
1920 kg/ m3
Reinforced concrete
2310 – 2700 kg/ m3
Curing time of RCC Members for different types of cement:
Super Sulphate cement: 7 days
Ordinary Portland cement OPC: 10 days
Minerals & Admixture added cement: 14 days
De-Shuttering time of different RCC Members
RCC Member
De-shuttering time
For columns, walls, vertical form works
16-24 hrs.
Soffit formwork to slabs
3 days (props to be refixed after removal)
Soffit to beams props
7 days (props to refixed after removal)
Beams spanning upto 4.5m
7 days
Beams spanning over 4.5m
14 days
Arches spanning up to 6m
14 days
Arches spanning over 6m
21 days
Cube samples required for different quantity of concrete:
Quantity of Concrete
No. of cubes required
1 – 5 m3
1 No’s
6 0 15 m3
2 No’s
16 – 30 m3
3 No’s
31 – 50 m3
4 No’s
Above 50 m3
4 + 1 No’s of addition of each 50 m3

About Author:

I am Thomas Britto here to share my experiences in the civil engineering field to all my readers.Today many students are struggling to buy books at high prices. So I decided to start a blog and share my experience and knowledge with all my readers.


Let's Get Connected: Twitter | Facebook | Google Plus

No comments